Saturday, August 30, 2008

Blog for client update and meeting minute request

@Kevin: hi Kevin, can you update the blog for client with following things, thanks Kevin :
  • The meeting minute (who took the meeting minute on friday would provide you this)
  • Project progress (write something to say that we have finished the requirement specification and client has agree on Acceptance Criteria), post the project time line picture if you can (i put this PDF in file exchange in BB already)
@Andrew: hi Andrew, can you update our blog with team meeting minute for last thursday, i will update the "things need to be done next after you post the minute" (leave a section called "things need to be done next" in the bottom of minute for me if you can). By the way, please save all the meeting minute documents in separate folder in your PC and for our blog only, you dont need to post the minute with formal structure, just say what we have done, what we have decided, who will do what and things need to be done next. And post the final Requirement and Development Plan to file exchange in BB. That would be great, thanks Andrew.

If you guys have any question (whatever it is - even dumbest one), feel free to speak it out and we all can answer it. Thanks guys

1 comment:

Kevin Chan said...

i have uploaded the final Requirement and Development Plan to file exchange in BB